COLLEGE OF DUPAGE ARCHITECTURE DESIGN + BUILD SUMMER STUDIO

Thursday, July 27, 2023

Hot Hot Summer

 We are making slow but steady progress in the hottest week of the year.  Today we stopped early to escape the heat, but we did get "most" of the OSB sheathing completed.  

We will be ready to start the siding soon!







Wednesday, July 26, 2023

Construction Week 03

We are sad to leave the air conditioned shop, but we also recognize that moving outside means substantial progress toward completing this project!  This week has been hot thought.





























Moving Day

 Hot.  Heavy.  But we got it outside, reassembled, and squared.  

















Construction Week 02

 This week we finished up framing work in the shop.  And then it was time to move outside.








Saturday, July 15, 2023

Construction Week 01

We have had a busy and productive first week of construction.  Here are some progress photos.  We are probably about 80% done with the framing.